Method statement example: a worked sequence, and the level of detail worth copying

Examples teach more than templates, because the thing worth copying is the level of detail rather than the headings. A step that says isolate supply is not a step. A step that says who isolates, how the isolation is proved dead, how it is locked, who holds the key and what happens if somebody needs the supply back is a step somebody can follow and a reviewer can accept.

Get asbestos quotes

A worked sequence, in outline

Take replacing a light fitting in an occupied office. Arrive and report to the building manager. Agree the working area and cordon it, including the floor below if the ceiling void is open. Confirm the circuit and isolate at the distribution board. Prove dead with an approved voltage indicator, proved on a known source before and after. Lock off and label, key retained by the electrician. Set up the access equipment on a clear, level floor. Remove and replace the fitting. Restore, test, re-energise, check operation. Clear the area, remove the cordon, hand back and record.

Why each of those steps is there

The cordon protects people who are not yours, which is the section 3 duty. Proving dead before and after on a known source is what turns an assumption into a check. Key retention stops somebody else re-energising the circuit while you are working on it. Handing back to a named person closes the loop, so the building manager knows the area is normal again.

What an electrical method statement example must show

Isolation, proving dead, lock-off and key control, in that order and with names. Plus the test instrument and its calibration, the safe working procedure if any part of the work must be done live and why that is justified, and the arrangements for restoring supply. An electrical method statement that does not describe proving dead has omitted the step the whole procedure exists for.

How to use an example without copying it

Read it for the grain of detail, then write your own sequence for your own job at that grain. Copying an example wholesale reproduces its assumptions about the site, and those assumptions are exactly what a reviewer checks. The value of the example is that it shows you how specific specific means.

Questions people ask about method statement example

What does a method statement example look like?

A numbered sequence from arrival to handover, with each step naming who does it, the equipment used and the control it depends on.

How detailed should each step be?

Detailed enough that the step could be followed by a competent person who has not done this job before, and checked by somebody who was not there.

What must an electrical method statement include?

Isolation, proving dead on a known source before and after, lock-off with key control, the test instrument and its calibration, and the arrangements for restoring supply.

Can I reuse an example for a different site?

Not as it stands. Reuse the structure and the level of detail, and rewrite the site-specific content, which is what a reviewer reads first.

How to write method statement text that a principal contractor will accept

Write it as instructions to the people doing the work, in the order they will do them, in the present tense and with no conditionals. Name the plant, the access equipment and the permits by the type actually being used. Put the numbers in where a number is the control: the exclusion zone, the load, the isolation point. Say who stops the job and on what trigger. Then read it back asking one question per paragraph, whether somebody who has never seen this site could follow it, and cut every sentence that is a statement of good intent rather than an instruction. A statement that says work will be carried out safely in accordance with all relevant legislation has said nothing.

Sources

Get an asbestos quote from contractors on HSE's own licence register

Free for duty holders and property owners. Your details go to contractors covering your area, not to a call list. We may email you about this enquiry and similar services from this site; opt out any time, including from the first message.

Related answers

Get asbestos quotesSearch the register